Highway 401 and Highway 4 (Colonel Talbot Road) Interchange Reconfiguration
& Highway 4 (Colonel Talbot Road) and Glanworth Drive Bridge Replacements

Construction
The following sections will be updated weekly to reflect construction updates and traffic impacts.
​​
Anticipated Work for the Next Month
March 24, 2025 to April 25, 2025:
-
Glanworth Drive and Structure
-
Installation of drainage tiles
-
Place engineered clay fill
-
Form bridge deck
-
-
New Colonel Talbot structure
-
Pile driving
-
-
Colonel Talbot Road North Portion
-
Remove contaminated soil from Printshop Property
-
Place engineered clay fill
-
Erosion and sediment control measures for winter shutdown
-
-
Littlewood Drive
-
Installation of drainage tiles
-
Topsoil stripping
-
Earth excavation cut/fill
-
​​​
Traffic Impacts for the Next Month
​​
-
Hwy 401 eastbound driving lane or high speed lane from 300 m to 1 km east of Colonel Talbot Road Underpass
-
Hwy 401 westbound driving lane or high speed lane from 400 m to 800 m west of Wonderland Road
-
W-N Off Ramp at Colonel Talbot Road and Hwy 401
-
S-W On Ramp at Colonel Talbot and Hwy 401
-
Colonel Talbot Road Northbound shoulder only from Glanworth to Decker
​​
Current Lane Closures - Week of April 14th, 2025
​​​
​The westbound on ramp from Colonel Talbot Road South to Highway 401 westbound (S-W Ramp) will be closed for offloading/removal of construction equipment and materials
-
Tuesday to Wednesday, April 15-16, 2025 from 7 am to 6 pm daily
​
Colonel Talbot Road northbound and southbound will intermittently reduced to a single lane controlled by flag persons between Littlewood Drive to Decker Drive
-
Tuesday to Thursday, April 15-17, 2025 from 7 am to 6 pm daily
​
ADVANCE NOTICE:
The westbound on and eastbound off ramps will be closed to traffic starting April 21, 2025 until end of day June 2, 2025.
​​​
​​​​​​The following section provides general information related to construction and does not change.
​
SUMMARY OF CONSTRUCTION BY YEAR
​2024 Construction Season:
-
Construct median piers for new Highway 4 (Colonel Talbot Road) bridge
-
Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge
-
Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median
-
Reconstruct Highway 401 median storm sewer and sewer crossings
-
Construct western realignment half of Tempo Road
-
Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place
-
Install HML
​
2025 Construction Season:
-
Construct new Highway 4 (Colonel Talbot Road) bridge offline
-
Construct abutments with approaches and install new girders for new Highway 4 bridge
-
Construct the Tempo Road Realignment
-
Construct new Glanworth Drive bridge and deck structure
-
Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place
-
Widen northern portion of Highway 4
-
Remove existing Glanworth Drive bridge
​
2026 Construction Season:
-
Construct new Highway 4 bridge deck and structure
-
Complete widening and realignment of Highway 4 except surface course paving
-
Construct new interchange ramps and speed change lanes
-
Remove existing Highway 4 bridge
-
Construct southbound lanes of Colonel Talbot Road
-
Construct realignment of Burtwistle Lane
​
2027 Construction Season:
-
Complete surface course paving and construction of raised median on Highway 4
-
Complete surface course paving of interchange ramps
-
Construct aesthetic monuments at Highway 4 Underpass
-
Complete remaining portions of median tall wall barrier