top of page
20230725_143406_edited.jpg

Construction

The following sections will be updated weekly to reflect construction updates and traffic impacts.

​​

Anticipated Work for the Next Month

March 24, 2025 to April 25, 2025:

  • Glanworth Drive and Structure

    • Installation of drainage tiles

    • Place engineered clay fill

    • Form bridge deck

  • New Colonel Talbot structure

    • Pile driving

  • Colonel Talbot Road North Portion

    • Remove contaminated soil from Printshop Property

    • Place engineered clay fill

    • Erosion and sediment control measures for winter shutdown

  • Littlewood Drive

    • Installation of drainage tiles

    • Topsoil stripping

    • Earth excavation cut/fill

​​​

Traffic Impacts for the Next Month

​​

  • Hwy 401 eastbound driving lane or high speed lane from 300 m to 1 km east of Colonel Talbot Road Underpass 

  • Hwy 401 westbound driving lane or high speed lane from 400 m to 800 m west of Wonderland Road 

  • W-N Off Ramp at Colonel Talbot Road and Hwy 401

  • S-W On Ramp at Colonel Talbot and Hwy 401

  • Colonel Talbot Road Northbound shoulder only from Glanworth to Decker

​​

Current Lane Closures - Week of April 14th, 2025

​​​

​The westbound on ramp from Colonel Talbot Road South to Highway 401 westbound (S-W Ramp) will be closed for offloading/removal of construction equipment and materials

  •   Tuesday to Wednesday, April 15-16, 2025 from 7 am to 6 pm daily

​

Colonel Talbot Road northbound and southbound will intermittently reduced to a single lane controlled by flag persons between Littlewood Drive to Decker Drive

  •   Tuesday to Thursday, April 15-17, 2025 from 7 am to 6 pm daily

​

ADVANCE NOTICE:

The westbound on and eastbound off ramps will be closed to traffic starting April 21, 2025 until end of day June 2, 2025.

​​​

​​​​​​The following section provides general information related to construction and does not change.

​

SUMMARY OF CONSTRUCTION BY YEAR

​2024 Construction Season:

  • Construct median piers for new Highway 4 (Colonel Talbot Road) bridge

  • Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge

  • Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median

  • Reconstruct Highway 401 median storm sewer and sewer crossings

  • Construct western realignment half of Tempo Road

  • Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place

  • Install HML

​

2025 Construction Season:

  • Construct new Highway 4 (Colonel Talbot Road) bridge offline

  • Construct abutments with approaches and install new girders for new Highway 4 bridge

  • Construct the Tempo Road Realignment

  • Construct new Glanworth Drive bridge and deck structure

  • Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place

  • Widen northern portion of Highway 4

  • Remove existing Glanworth Drive bridge

​

2026 Construction Season:

  • Construct new Highway 4 bridge deck and structure

  • Complete widening and realignment of Highway 4 except surface course paving

  • Construct new interchange ramps and speed change lanes

  • Remove existing Highway 4 bridge

  • Construct southbound lanes of Colonel Talbot Road

  • Construct realignment of Burtwistle Lane

​

2027 Construction Season:

  • Complete surface course paving and construction of raised median on Highway 4

  • Complete surface course paving of interchange ramps

  • Construct aesthetic monuments at Highway 4 Underpass

  • Complete remaining portions of median tall wall barrier